In view of this it is proposed that the following households be considered as Project Affected Households :
1) All households in those settlements which lie entirely within the PAA
2) All households in those settlements where more than 75 percent of the households lie within the PAA
3) Only those households which lie in the PAA, in settlements where less than 75 percent of household lie within the PAA
A detailed survey of all Project Affected Households (between Vasna Barrage and Subhash Bridge) was conducted between the 4th week of February and 1st week of March 1998. The total number of households physically affected by the works proposed as part of the SRFD Project is 4400.
Project Affected Economic Activities
Drawing shows the location of economic activities that are carried out in the Project Affected Area between Subhash Bridge and the Vasna Barrage. They include: 1) laundering, 2) (vending in) informal markets, 3) sand collection, 4) cultivation - between December and April and, 5) dyeing. A reconnaissance survey has suggested that upstream of Subhash Bridge sand collection and cultivation are the only activities being carried out between the riverbanks.
With the proposed submergence of the riverbed 15 km upstream of the Vasna Barrage it will not be possible to collect sand from the riverbed nor will cultivation be possible there. Laundering, dyeing and the holding of informal markets will also not be possible in the manner that these activities are presently being carried out. All five activities may therefore be considered as Project Affected Economic Activities (PAEA).
Objectives of the Resettlement and Rehabilitation Component
-
It is proposed that as part of the SRFD Project those persons whose residences or activities are adversely affected by the proposed works should be adequately compensated through resettlement and rehabilitation measures.
-
It is proposed that, to the extent it is possible, the SRFD Project should bring about a positive transformation in the lives of people affected by the project. The project should be seen as an opportunity to improve the lives of people affected by the project and that the disruption cause by resettlement should be kept at a minimum. This criterion should be used to structure the resettlement and rehabilitation measures.
-
It is proposed that an innovative and effective mode of implementing the resettlement and rehabilitation component of the project should be adopted so that the project becomes a model that may guide future redevelopment projects. It is proposed that, to the extent that it is effective, project-affected persons should be directly involved in the process of resettlement and rehabilitation.
Resettlement and Rehabilitation Measures
Provision of Serviced Resettlement Sites
Land use drawing shows the three sites where it is proposed to resettle the 4400 Project Affected Household. The three sites are as follows:
| 1 |
Dudheshwar Relocation Site |
8.64 |
| 2 |
Gaikwad Haveli Relocation Site |
2.81 |
| 3 |
Paldi Relocation Site |
4.03 |
| Total |
15.48 |